Reminder: The Next HA Rollover is Coming March 9th – We Need You to Perform a Connectivity Test!

Twice each year, CU*Answers tests our ability to redirect CU*BASE core-processing from our production data center in Kentwood, MI to our high-availability (HA) data center in Yankton, SD. The next HA rollover is scheduled for Sunday, March 9th.

The rollover is scheduled to begin at 3:00 AM ET on Sunday, March 9th with the rollback planned for 3:00 AM ET on Sunday, March 16th. During both the Rollover and Rollback procedures, the following services will be interrupted for approximately 60 to 90 minutes: CU*BASE/GOLD, CU*Talk audio response, and It’s Me 247 online banking (a splash page will be presented). ATM and credit card transactions will operate in stand-in mode at the switch until systems are back online.

As a reminder, we strongly encourage that someone at each branch tests connectivity to the HA data center from a GOLD workstation prior to the Rollover event.  If you have not yet done so, please use the links below to perform one or both of the connectivity tests.

Please contact the CU*Answers Network Services Help Desk at helpdesk@cuanswers.com if the tests above are unsuccessful. Failure to complete the tests may result in CU*BASE/GOLD connectivity issues on the morning following the March 9th rollover event.