Rescheduled from our original targeted date of March 17th, the high-availability rollback event will now be occurring this weekend. The rollback process will begin Sunday, April 7th at 3:00 AM ET. During this time, there will be a period of approximately 60 to 90 minutes that will include an interruption to the following services: CU*BASE/GOLD,… Read more »
Reminder: HA Rollback This Weekend
This is a reminder of the high-availability rollback event that will be occurring this weekend. The rollback process will begin Sunday, March 17th at 3:00 AM ET. During this time, there will be a period of approximately 60 to 90 minutes that will include an interruption to the following services: CU*BASE/GOLD, CU*Talk audio response and… Read more »
Reminder: The Next HA Rollover is Coming March 10th – We Need You to Perform a Connectivity Test!
Twice each year, CU*Answers tests our ability to redirect CU*BASE core-processing from our production data center in Kentwood, MI to our high-availability (HA) data center in Yankton, SD. The next HA rollover is scheduled for Sunday, March 10th. The rollover is scheduled to begin at 1:00 AM ET on Sunday, March 10th with the rollback… Read more »
Network Maintenance Project Scheduled for Sunday, March 10th
As a reminder, CU*Answers will be performing our next CU*BASE high-availability (HA) rollover on Sunday, March 10th. That same morning, teams will be rolling over online and mobile banking systems to servers at our secondary data center. These rollovers are in preparation for a maintenance project at our production data center that will include… Read more »
Reminder: The Next HA Rollover is Coming March 10th – We Need You to Perform a Connectivity Test!
Twice each year, CU*Answers tests our ability to redirect CU*BASE core-processing from our production data center in Kentwood, MI to our high-availability (HA) data center in Yankton, SD. The next HA rollover is scheduled for Sunday, March 10th. The rollover is scheduled to begin at 1:00 AM ET on Sunday, March 10th with the rollback… Read more »
Network Maintenance Project Scheduled for Sunday, March 10th
As a reminder, CU*Answers will be performing our next CU*BASE high-availability (HA) rollover on Sunday, March 10th. That same morning, teams will be rolling over online and mobile banking systems to servers at our secondary data center. These rollovers are in preparation for a maintenance project at our production data center that will include… Read more »
Reminder: The Next HA Rollover is Coming March 10th – We Need You to Perform a Connectivity Test!
Twice each year, CU*Answers tests our ability to redirect CU*BASE core-processing from our production data center in Kentwood, MI to our high-availability (HA) data center in Yankton, SD. The next HA rollover is scheduled for Sunday, March 10th. The rollover is scheduled to begin at 1:00 AM ET on Sunday, March 10th with the rollback… Read more »
Online Banking Rollover Event Tomorrow – Updates to be Posted on the CU*BASE Alerts Page
Don’t forget: tomorrow morning, we will be performing a Rollover for It’s Me 247 online/mobile banking (OLB) environments, as well as BizLink 247 online banking for business. The Rollover event is scheduled to begin at 5:00 AM ET (2:00 AM PT) on Wednesday, February 14th, with the rollback scheduled for 6:00 AM ET (3:00 AM… Read more »
The Next HA Rollover is Coming March 10th – We Need You to Perform a Connectivity Test!
Twice each year, CU*Answers tests our ability to redirect CU*BASE core-processing from our production data center to our high-availability (HA) data center. The next HA rollover is scheduled for Sunday, March 10th. This rollover will enable support teams to perform planned network maintenance at the primary production data center without disrupting core processing. The rollover… Read more »
Mark Your Calendar for the Next Online Banking Rollover
On Wednesday, February 14th, from 5:00 AM to 6:00 AM ET (2:00 AM to 3:00 AM PT), we will be performing a Rollover for It’s Me 247 online/mobile banking (OLB) environments, as well as BizLink 247 online banking for business. During this one-hour period, online and mobile banking will run live on servers at our… Read more »
AFG integration
The Auto Financial Group direct balloon lending integration with CU*BASE is live! AFG provides so many benefits to your credit union and your members alike. Explore this integration to see if it is the right fit for you!
Learn More
In Case You Missed It…
Take a look back at some important topics from the first half of December 2024! View Topics
Conversations On…
A new way to interact with your CUSO and your peers. This new series will take traditional focus groups to a whole new level. Learn More
GOLD Updates
The next GOLD updates are currently scheduled for:
- Online/Partner CUs
- 25.05 May. 18, 2025 (Sunday)
- Self Processing CUs